DAWSONVILLE, GA. – Georgia Department of Transportation construction partners will start paving on State Route 183 at the intersection of State Route 52 in Dawson County, Monday, June 24 and will continue through Friday, June 28.
Paving will occur during the hours of 8 a.m. to 5 p.m. Flagging will be done during this time to allow traffic to pass through safely. Travelers should expect short delays during these dates and times.
After paving is complete the required striping and signage will be installed and then on July 1, 2019 traffic will be shifted and the intersection will operate as a roundabout.
The information you provide to the Georgia Department of Transportation will be used solely by GDOT. The Department does not sell or offer a subscriber’s personal information to third parties for marketing purposes. To no longer receive this e-news letter, please select “unsubscribe from this list” below.
Fetch Your News is a hyper local news outlet that covers Dawson, Lumpkin, White, Fannin, Gilmer, Pickens, Union, Towns and Murray counties as well as Cherokee County in N.C. FYN attracts 300,000+ page views per month, 3.5 million impressions per month and approximately 15,000 viewers per week on FYNTV.com and up to 60,000 Facebook page reach. If you would like to follow up-to-date local events in any of those counties, please visit us at FetchYourNews.com



Leave a comment